+7 499 460-63-47 RU

COMMERCIAL DISPUTES / 02

Construction and contracting disputes

A construction dispute is rarely about a single figure: volumes, quality, deadlines, extra works and retentions all tangle into one story. We unpick it from the as-built documentation, work with engineers and experts, and act for the employer, the general contractor or the subcontractor.

Call: +7 (499) 460-63-47
For whom
Companies and entrepreneurs
Format
Moscow and remotely across Russia

What is happening

The contractor has completed the works and sent the KS-2 completion certificates and KS-3 cost statements, but the employer is silent or returns them with vague remarks such as 'poor quality'. Nothing is paid, yet the building is already in use.

The employer sees the programme has slipped and quality is questionable, and wants to terminate, recover the unearned advance and bring in another contractor. That has to be done without ending up paying for works effectively accepted and without losing the right to a penalty.

A subcontractor carried out extra works on the general contractor's verbal instructions, and the variation was never signed. The general contractor refuses to pay, relying on the fixed contract price.

What the law says

  • The relationship is governed by Chapter 37 of the Civil Code on work contracts, including the special rules on construction contracts; for state and municipal employers Federal Law No. 44-FZ of 5 April 2013 "On the Contract System for the Procurement of Goods, Works and Services to Meet State and Municipal Needs" (the Public Procurement Law) also applies.
  • A unilateral completion certificate can be declared invalid only if the court finds the employer's reasons for refusing to sign justified (Article 753 of the Civil Code). So unexplained silence usually works against the employer.
  • As a general rule a contractor cannot require payment for extra works not agreed with the employer; the exceptions concern situations where immediate action was needed in the employer's interest.
  • The employer may withdraw at any time on paying for the works performed (Article 717 of the Civil Code), or withdraw because of the contractor's breaches; the ground chosen determines the consequences, including damages.
  • Disputes over volume and quality are almost always resolved by a construction expert examination; much depends on the questions put to the expert and the documents they receive.
  • Release of retentions and security payments is governed by the contract; what happens to them on termination is often a dispute in its own right.

What we do

  • We analyse the contract, estimates, programmes and as-built documentation and reconstruct the chronology of the works and correspondence.
  • With engineers and quantity surveyors we assess volumes and quality before any court action.
  • We prepare a reasoned refusal to accept or, conversely, the documents to support a unilateral certificate.
  • We frame the questions for the expert, take part in choosing the expert body and attend the site inspection.
  • We calculate the value of the works, penalties, damages and the final account between the parties on termination.
  • We represent the company in the commercial court, including in disputes under state and municipal contracts.

What we will need from you

  • The works contract with annexes, estimates, programmes and variations.
  • KS-2 certificates, KS-3 statements, hidden-works inspection reports, the general works log and as-built documentation.
  • Correspondence, minutes of site meetings, instructions from technical supervision and the employer.
  • Photos and video of the site, if available.
  • Payment records and details of advances and retentions.

HOW THE WORK IS BUILT

How the work is built

Documents

We study the contract and as-built documentation and identify the disputed items.

1–2 weeks

Technical review

With engineers we assess volumes and quality and, where needed, obtain a specialist's report.

depends on site size

Claim letter

We send a claim letter or reasoned objections and try to settle.

30 days

Court

We run the case, frame the questions for the expert, attend the inspection and examine the expert.

several months or more

QUESTIONS

Frequent questions

The employer has not signed the certificates for three months. Can we sue?

Yes. If the employer has not sent a reasoned refusal, the contractor can issue a unilateral certificate and claim payment. Before suing we check how and when the certificates were delivered and whether the employer has documented complaints: that determines how the court will view the unilateral certificate.

Is a pre-trial expert report worth it if the court will appoint its own expert?

Often, yes. A specialist's report helps assess the prospects before incurring court costs, frame the right questions and justify an application for a court-appointed examination. The court may also take it into account as documentary evidence.

Do you handle disputes under public contracts?

Yes, including contracts concluded under the Public Procurement Law. These disputes have their own features: strict rules on changing price and deadlines, penalties calculated by a set formula, and the risk of being entered in the register of unreliable suppliers if the employer withdraws unilaterally.

NEXT STEP

Let us discuss your situation

The consultation is free of charge when an engagement agreement is signed: on it we say what has to be done and by when.

Call: +7 (499) 460-63-47